Thursday, 3 December 2015
Wednesday, 12 August 2015
Primavera P6 Tips Part 2- How To De-progress A Schedule In P6
- Choose Enterprise,
Projects and select the Calculations tab.
Choose to "Link Budget and At Completion for not started
activities" and "Reset Remaining Duration and Units to
Original".
- Choose View,
Columns and add the columns for Actual Labor Units, Actual
Nonlabor Units.
- Choose Tools,
Schedule and set the data date equal to the Project Start Date
and schedule. To find the Project Start date, choose Enterprise,
Projects. Click on the Dates tab and note the
Planned Start date.
- For
the first activity in the list, set the Actual Labor Units to 0. Highlight
the activities in this column and choose Edit, Fill Down.
- For
the first activity in the list, set the Actual Nonlabor Units to 0.
Highlight the activities in this column and choose Edit, Fill
Down.
- Choose Tools,
Global Change and run the 1st Global Change. This will set
the Actual Material Units to zero.
- Run
the 2nd global change which sets the activity status to Not Started.
Activity Resource Assignments
Resource Type equals Material
Actual Material Units = 0
Activities
Where Activity Status is not equal to Not Started
Activity Status equals Not Started
Activities
Where Activity Status is equal to Not Started
Remaining Duration = Original Duration
Primavera P6 Tips Part 1-How to Filter Out Activities That Are Not in the Baseline
You have to use both the start and finish if there are Milestones. This filter will show activities that are not in the Baseline.
Tuesday, 11 August 2015
Why Schedule Risk Analysis is required for projects?
The Value
CPM is Optimistic
If again, each activity takes 5 days to execute, the project should complete at the end of day 5. However, what happens if activity A takes 6 days to execute? The project completion will slip to day 6 and there’s nothing we can do to Activity B to improve the situation. In fact, if B has any effect at all, it will only be to delay the project further.
|
|
|
| On-Time/Early | On-Time/Early | On-Time/Early |
| Late | On-Time/Early | Late |
| On-Time/Early | Late | Late |
| Late | Late | Late |
Summary
Tuesday, 28 July 2015
7 Important Project Management Mysteries
- Define the scope and objectives
- Define the deliverables
- Project Planning
- Communication
- Tracking and reporting project progress
- Change management
- Risk management
Monday, 27 July 2015
How Do You Control a Project?
2.Budget and plan the execution of the scope
3.Execute the scope per the plan
4.Control the scope
5.Manage the budget variance
As you know, scope is the single most important variable in defining & controlling the cost of a project. As the with the above project, not planning and developing the scope lead to their downfall.
It’s Difficult! Like you, I know in practice developing the scope difficult to do. However, when it comes to managing a project, it’s “garbage in equals garbage out.”
Scope wrong = estimates wrong.
Scope wrong = schedule wrong.
Scope wrong - resource allocations wrong
The wrong scope can cause a lot of difficulty and discomfort to a project manager. I didn’t like it when I started out, so I took steps to successfully develop scopes for various size projects. So if you
are suffering the pain and discomfort from scope definition problems, and you want to sleep well at night, You need to put in the time, money and effort in determining your total scope.
Leadership Style
- Having
the vision to plan, organize and set objectives
- Being
inspiring, making people proud to be on your team.
- Being
assertive.
- Keeping
calm during a crisis, avoiding visible panic.
- Learning
from your failures - this is where experience comes from.
- Understanding
the skills of your team and delegating tasks accordingly.
- Motivating
your team members.
- Mentoring
and coaching junior members of the team.
- Providing
constructive criticism.
- Making
logical decisions (need to know project management fundamentals to do
this)
- Persevering
when things are not going well.
- Being
able to respond to changing situations.
- Accepting responsibility for the mistakes and wrong decisions
- Developing
and implementing the project execution plan and project schedule
- Communicating
the project status to management
- Contracting
for engineering services
- Project
team leader for project contacts and organizing drawing reviews.
- Responsible
for reporting to management.
- Manage
engineering and procurement
- Review
construction bid packages
- Coordinate
construction contracting
- Manage
permitting
- Provide
constructability expertise
- Assist
field efforts during construction
- Coordinate
commissioning and startup
- Coordinate
all technical issues during construction
- Handling
project change and tracking change orders
- Responsible
for project close out.
Monday, 6 July 2015
Sample Delay Analysis
Try the following link for some sample delay analysis.
https://www.mdpi.com/2075-
Good Luck
Tuesday, 30 June 2015
How To Convince Your Boss To Pay For Your Project Management Training
With advanced technology, ever-evolving market and competition, it’s critical for project controllers, schedulers and planners in the construction industry to stay on top of their game. Continuing education and project management training are the keys to advancing skills for controllers, schedulers and planners in the construction field. But how do you convince your boss to pay for your training? The simple answer is to roll up your sleeves and create a mini-proposal that hits home. And be ready to answer some questions. With a well-defined proposal that highlights all of the benefits for the company, your boss will be eager to take out the company wallet. Here are some steps outlining what to cover.
The Impact on Current Projects or Role
While generalized training is good, timely training can be utilize on the job right away. Your boss will want to know how what you’ve learned can be used on the current corporate projects. Be prepared to give some real-time answers. For example, management software training will allow you keep track of the current project’s progress and easily collaborate with workers on the project. This approach is a home run. It directly emphasizes the positive effective of the training on your role and the company.Certifications and Degrees
If your goal is to attain a certificate or degree, present the larger learning goal in a manner that shows how the learning is directly related to the company’s needs. Outline how the specific skills learned from certificate-oriented instruction will close skill gaps. And if you’re seeking a degree, ensure that it lines up with your career path within the company. This way, your larger learning goal is strategic and not opportunistic.Useful and Cost Effective
Present the reasons why the training is a good fit and the best value. Your boss will want to ensure that you’ve done your research before he reaches into the company funds. Prepare a list of key learning outcomes from the training, such as competence in analyzing cost statistics or preparing documents in compliance with regulations. With define learning outcomes and a good value, your boss is more likely to make the decision that the training makes good financial sense.Company Growth and Profits
The goal of a business is to grow and make money. Create a factual list of how the training will have a positive impact on profits, such as streamlining the construction and reporting process, implementing new methods, accurate analysis of costs and the planning of new projects. Prepare a current list of where the company is now and use charts and graphs to display projected growth as a result of the training.When you step into the boss’s office to ask for funds for professional training, you’re really a sales person. You’ve got to sell the worthiness of the training. Follow these steps, and you’ll win the jackpot.
Monday, 29 June 2015
About Me
Shervin has worked on a wide range of projects, and in countries
from Iran to Syria, and Malaysia. He has been responsible for major oil and gas
projects, and power plant projects. Shervin is a Certified PMP and RMP by
PMI and PRINCE2 by APMG and Team Lead Assessor of the Iran National Project
Excellence Award. He is specialized in schedule risk analysis, estimate &
schedule assurance reviews, integrated portfolio schedule, project control,
benchmarking, and Earned Value Analysis. Shervin has 20+ years of industrial
experience in consulting oil & gas projects, both upstream and downstream. Shervin
worked in various locations including Iran, Syria, and Malaysia.
Project Management Specialist for multi-billion dollar projects with 20+ years of leadership success on multi-billion-dollar EPCIC and LSTK mega-projects. Expert regarding onshore and offshore oil/gas EPCIC and PMC contracts.
Currently, directing Schedule Risk Analysis for Peninsular Malaysia Operation & SBO mega-projects for Petronas Carigali. Directed SRA for 32 projects, including the company’s largest project, Iraq GARRAF FDP, delivering significant savings by migrating SRA to in-house function. Authored planning and scheduling guidelines and procedures, and implemented EVM.
Previously, guided project planning for €5.5-billion South Pars Gas Field Development Mega-Project is among the largest projects of its kind globally, with Industrial Projects Management of Iran.
Well-versed in schedule health check reviews and schedule development from concept to commissioning, using Primavera 6 20.12 and MS Project. Experienced in establishing planning and project control procedures and provide benchmark analysis for upstream projects. Knowledge to measure physical progress based on earned value principles, prepare critical path schedule, lead time impact analysis, and issue recommendations.
Talent leading functional project teams and managing critical
timelines. Finesse maintaining communications between the engineering
disciplines, departments with the project team, major stakeholders, and
clients. Experienced in presenting complex proposals and reports to clients and
senior management.


