GOAL
This
post explains how to remove progress from a schedule in P6 so that all percent completes are zero and there are no actuals.
Please
perform the following steps to remove the progress from your project in the
order that they appear in this list:
- Choose Enterprise,
Projects and select the Calculations tab.
Choose to "Link Budget and At Completion for not started
activities" and "Reset Remaining Duration and Units to
Original".
If the Calculations Tab is not showing, it needs to be
added. Go to the Projects view and right-click in the details section at
the bottom. Choose 'Customize Project Details'. Then select the Calculations option
on the left and bring it over to the right. Then click OK.
- Choose View,
Columns and add the columns for Actual Labor Units, Actual
Nonlabor Units.
- Choose Tools,
Schedule and set the data date equal to the Project Start Date
and schedule. To find the Project Start date, choose Enterprise,
Projects. Click on the Dates tab and note the
Planned Start date.
- For
the first activity in the list, set the Actual Labor Units to 0. Highlight
the activities in this column and choose Edit, Fill Down.
- For
the first activity in the list, set the Actual Nonlabor Units to 0.
Highlight the activities in this column and choose Edit, Fill
Down.
- Choose Tools,
Global Change and run the 1st Global Change. This will set
the Actual Material Units to zero.
- Run
the 2nd global change which sets the activity status to Not Started.
1st Global Change:
Subject
Area:
Activity Resource Assignments
Activity Resource Assignments
If:
Resource Type equals Material
Resource Type equals Material
Then:
Actual Material Units = 0
Actual Material Units = 0
2nd Global Change:
Subject Area:
Activities
Activities
If:
Where Activity Status is not equal to Not Started
Where Activity Status is not equal to Not Started
Then:
Activity Status equals Not Started
Activity Status equals Not Started
If this process is not used you may encounter the following error:
"Cannot set status to Not Started if activity has
actuals."
3rd Global Change:
Add duration to activities by running global change for Not
Started activities
Subject Area:
Activities
Activities
If:
Where Activity Status is equal to Not Started
Where Activity Status is equal to Not Started
Then:
Remaining Duration = Original Duration
Remaining Duration = Original Duration
Reference: Oracle P6 Support